RESULTS 2019-2020: DESIGN AND CONSTRUCTION

news-bg.jpg
At the expense of the Kaliningrad Region Development Corporation, the following infrastructure was built:

• Industrial park "Khrabrovo" electric power station 110 kV "Khrabrovo", with a capacity of 39 MW.
• Industrial park "Chernyakhovsk" 110 kV electric power station "Industrialnaya", capacity 34 MW.
• Power supply networks in the Khrabrovo Industrial Park. More than 50 km of electrical cable, 5 distribution substations and 4 transformer substations have been built.
• Transport infrastructure of the industrial park "Khrabrovo": a road was built, length 2.18 km.
• Engineering infrastructure of the industrial park "Khrabrovo": built a sewerage network of communication networks, length of 2.3 km.
• Engineering infrastructure of the Khrabrovo industrial park: the gas supply network is under construction. Length 2.5 km.
• We continue to develop the territory of the Khrabrovo industrial park, this year we have developed design for the internal engineering infrastructure of the Khrabrovo industrial park, which we plan to build in 2021:
• water supply network. The length is 4.5 km.
• domestic sewerage network. Length 2.2 km.
• rainwater drainage networks. Length 2.22 km.
• road. Length 0.376 km.